by Michelle Saport |
彩神vlll争霸 Drive will experience a full-closure the weekends of Aug. 8 & 9 and Aug. 15 & 16. These closures are necessary for Neeser Construction to safely connect Mallard Lane to 彩神vlll争霸 Drive.
彩神vlll争霸 Drive will be closed from south of Widgeon Lane to Alumni Drive. The closures will be in effect between 8 p.m. Friday and 6 a.m. Monday for both weekends. The work will entail:
- Aug. 8 & 9: Installation of a storm drain across 彩神vlll争霸 Drive and Mallard Lane and construction of medians
- Aug. 15 & 16: Paving work around the 彩神vlll争霸 Drive and Mallard Lane intersection
The project team discussed trying to accomplish this work through individual lane closures; however, this would be impractical because of the nature of the work. Condensing the work to these two weekends allows Neeser to complete the work quickly and safely before the fall semester begins.
For up-to-date information on construction and maintenance activities, check the Facilities Blog at .